Client: Emcor

Project: Colebourne Inclusive School (095)

Completed: October 2008

Colebourne Inclusive School

Colebourne & Beaufort Inclusive School

This was an EMCOR development to coordinate of all the services for the new building for Colebourne and Beaufort Inclusive School.

This involved all distribution services throughout the building as well as all of the plantrooms. The suspended air handling plant area also needed loading calculations to work out the suspended load on the steel structure and determine bracketting points..

This project was complicated by the fact that the initial design concept for the services layout could not be followed as it was not accepted by the architect. We therefore had to 'improvise'  a route through a tight building whilst maintaining the strict architectural rules for service obscurement.