Background
The new Nationwide building headquarters in Swindon was a refurb of a building erected in the eighties.
Approach
We first went down there during the strip-out phase, firstly to get a cloud point survey done and also to assess what was being discovered during the strip-out that we needed to know for the coordination.
Riser locations were designed but couldn’t be located until we had investigated the site and worked out drop locations with the site team.
From the survey we were able to position the fan coil units in the appropriate bays then work out how many branches from the furthest to get back to the riser. Taking account of the steel lattice beam structure we were able calculate the distances and tolerances we needed to create a completely self draining system and fit all the other services around it.
Result
The result was a well serviced, highly maintainable building that looks great and projects the image wanted by Nationwide
Achieve complete coordination of all building services in your commercial refurbishment project
123 Victoria
Background 123 Victoria was refurbished to provide a high specification Retail, Commercial and CAT 'A' and...
Stockley Park
Background This is a state-of-the-art broadcast facility for television. It has a distinctly space age interior...